Finish Date in the Project Definition / Network Header

Former Member
0 Kudos

Dear Experts

When I am creating project through CJ20N, system by default putting current date as finish date. for both project definition and network header.

How can I make it start date.

Thanking you.

Best Regards,

Abdul.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Change your scheduling type for WBS to be backwards in WBS scheduling parameters(transaction OPTQ)and also change the scheduling type for network in network scheduling parameters(OPU6) 'backwards'. System will ask you to enter the finish date.

Regards,

Mahendra

Former Member
0 Kudos

Dear mahendra,

I have already maintained "backwards" both in OPTQ and OPU6, still system proposes by default the finish date not the start date.

Thanks

Abdul.

Former Member
0 Kudos

Check out your project, is it created before you change these configuration parameters. In normal circumstances, it should work.

Sorry I misunderstood, if you want system to ask you to put the start date enter scheduling type in both transactions as 'forward scheduling'.

Regards,

Mahendra

Edited by: Mahendra Dighe on Jan 28, 2010 7:02 PM