Dear Experts
When I am creating project through CJ20N, system by default putting current date as finish date. for both project definition and network header.
How can I make it start date.
Thanking you.
Best Regards,
Abdul.
Change your scheduling type for WBS to be backwards in WBS scheduling parameters(transaction OPTQ)and also change the scheduling type for network in network scheduling parameters(OPU6) 'backwards'. System will ask you to enter the finish date.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check out your project, is it created before you change these configuration parameters. In normal circumstances, it should work.
Sorry I misunderstood, if you want system to ask you to put the start date enter scheduling type in both transactions as 'forward scheduling'.
Regards,
Mahendra
Edited by: Mahendra Dighe on Jan 28, 2010 7:02 PM
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.