Production order Basic Start and Basic Finish Dates

Hi All,

If I use Lead Time Scheduling for my production orders, please guide me what are all the times will be accounted to compute Production order Basic Start and Basic Finish Dates.

Thanks in Advance.

Former Member
Former Member replied

Hi Madan,

In addition to others view, Pl. refer the following link. It explains with Graphical representation for easy understanding. (Pl. see at the end of the doc.)

http://help.sap.com/saphelp_40b/helpdata/en/f4/7d297144af11d182b40000e829fbfe/content.htm

Madhava