on 01-28-2010 12:08 PM
Hi Experts,
We have just changed the scenario from classic to ECS. When I copy an old SC created in classic scenario, to a new SC in extended, the follow on document (SRM-PO) can't get created.
If I activate transaction BBP_PD and look into the new SC it has status, I1111-Item in transfer status.
How can I get the SRM-PO created from this SC?
Best regards Kim
Hi,
Has PO been created?. Has PO been replicated?
If so, please check if CLEAN_REQREQ_UP and bbp_get_status_2 is scheduled.
Regards
Azad