on 01-28-2010 10:39 AM
Hi,
During incoming inspection, I am having 2 categories for vendors. One is self ceritified vendor- Dynamic Modification rule during incoming inspection and other is non self certified vendor for whom all incoming lots needs to be inspected.
I am maintaing one inspection plan with 2 group counters one for DMR (for self certified vendors) and other without DMR (for non self certified vendors).
Vendor status will change from self certified to non self certified, if PPM goes beyond 10000. How can we change the inspection status of this vendor from DMR to without DMR.
Thanks
VV
not finding astandard solution may have to look for a development
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have handled the self certification scenario by selecting "No inspection" in the Inspection Control field of Q-Info Record. This eliminates the need of having two Inspection plans or for removing and applying DMR in the inspection plans. Switching over from Self certified to Non self certified status can be done by changing the selection in the Inspection control field of Q-Info record to "Inspection Active if vendor is not certified". Although the switchover will have to be done manually whenever ppm goes above the acceptable level, yet it is easier than manually removing or applying DMR in the inspection plan. Even I would appreciate any suggestion that can help in automatic switchover based on ppm level.
Hi
Automatically system can not change the DMR or DMR level.
You have to do it manually ( by removing DMR) or by tresetting the level in QDl2
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.