Hi

scenario : i've maitained milestone billing for 3 milestone say 25% for one month and 15% on another month, and 10 % on final delivery and i get 50% advance with the po. so when i save my sales order my payment term should be showing 50% advance and 25%& &15% and 10%Milestone, i've created my billing plan accordingly and i've assingend the same to my billing document type also but still i'm not able to excute my billing

Vinz..

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi vinz,

in your milestone billing are you using the same billing doc type for the initial 50% and the remaining terms or you are using different billing types. if you using the same billing type can you use a different billing type for the initial 50% and do an order related billing for the same and check