Hi,
Some POs being submitted and approved are not reaching their
suppliers,When we checked in BBP_PD we are getting the Error "BBP_PD
428 Enter exactly one partner of type Vendor",I have Checked the Table
CRMD_PATNER and there are 4 entries for the GUID.
I have checked in the following way
1). CRMD_ORDERADM_H -> Pick the GUID and pass it to table CRMD_LINK (
to the field GUID_HI).
2.) Select the GUID_SET where OBJTYPE_HI = u201C05u201D and OBJTYPE_SET = u201C07u201D
3) Pass the GUID_SET value to table CRMD_PARTNER (to the field GUID).
The error is coming up due to the 4 entries in CRMD_PATNER?
Appreciate you'r Inputs on this.
Thanks
Rakesh.
Note 959528 - During PO creation wrong error message BBP_PD 428
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.