Hi Experts,
I have a requirement that
1.Is Plant level changes are possible after creation of project structure in Ps ?
2 Is changes possible after assigning of BOM to WBS?
3.Is changes possible after any confirmation and consumption of material in PP?
Here we r extending the requirement to another plant .As of now we are operationg from the single plant.
If possible please provide the solution
Thanks in Advance...
Regards,
Madam.
Hi Madan,
1.Is Plant level changes are possible after creation of project structure in Ps ? Yes, it can be changed
2 Is changes possible after assigning of BOM to WBS? Yes, it can be changed
3.Is changes possible after any confirmation and consumption of material in PP? No in the network activities but it can be changed in the WBS element (as fas as I know)
Best regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.