on 01-27-2010 5:53 AM
in report S_ALR_87013558, under one investment program and WBS element, we can see details of budget/actual/commitment,
but under RemOrdPlan column, it shows total of 233390 USD, we drill down to the network level, but every network/activity level for RemOrdPlan is zero, how can I know the details of 233390? which table can i use to find valuation type 25, which defined Remordplan?
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
remove the plan cost variant from assigned network header-control tab......and save.....
remaining order plan will be removed...
Regards
Ashis