Resource dependent lot size determination

Former Member
0 Kudos

Dear Experts,

For my client's business requirements, I have to consider resource dependent lot size istead of using lot size in produt master.

If someone has a lights on this situation, please guide me.

Thanks in advance for your cooperation.

Regards,

Lee, Seung Won

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Resource dependent lot sizes are configured in the PPM, Kindly maintain the lot sizes in PPM ( in Production version of ECC).

The planned orders then will automatically pick those ppm which have the Machine relevant lot sizes in the PPM.

regards

Virender

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In standarad SAP there is no provision for lot size determination baseed on resource. You can have lot size based PPM and PDS.Here you candefine multiple PPM containing different resources with min and max lot size. Here PPM will be based on lot size of procurment element.

Regards,

Santosh