Hello Gurus

I have completed one inspection lot with UD and still the stock is pending in the qc stock

and in the inspection lot the quantity is still in the postings as pending and material document is also created and

but stock not moved from quality to unrestricted

\

How to solve this

Thanks in advance

Rajesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi

Go to qa32>enter material>select the inspection lot with status UD SPRQ

go to inspection stock posting screen & enter the Qty in "Unrestricted stock"

save.

Now chaeck the status of the lot must be UD SPCO

Regards

Sujit

Former Member
0 Kudos

thank You for the Reply

It is giving status check error