TECO Status on WBS Element

shareeq_hussain
Active Participant
0 Kudos

Dear Experts,

We have set the status to TECO for a WBS Element.

But it is allowing CAT2 Entry for the Activity Attached to the WBS Element.

I would like to know if there is a Status to Block costs , but not Revenues

Regards,

Shareeq

Edited by: K M AHAMED SHAREEQ HUSSAIN on Jan 26, 2010 12:55 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In TECO,you can post the actual cost,it is open from accounting point of view and closed from logistics point of view that means you cant create a new PR/PO in TECO status.

So create a user status and prohibit the business transactions you wish.

Muzamil

Former Member
0 Kudos

Hi Gurus,

I have a problem also with my WBS Element's status... maybe you can help me...

We have some cost orders related to some WBS Elemetns. We want to be able to close first the WBS Element, and leave the cost order available for new postings, only in the COST ORDER, and when necessary, close the cost order. But SAP does not allow to close a cost order if it's WBS element is close. It gives CJ656 message, but i can't make this message only as a warning.

Do you have any idea or clue about how to avoid this problem?¿?

Thanks a lot!!

Regards

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

use the user status functionality to block costs when set to TECO as required, you can allow revenues