on 01-25-2010 3:24 PM
I am running SRM 7.0 SP 5.
I have set up customizing for output control for Action Profile BBP_PD_BID as follows:
Processing Time: Processing when saving document
Processing time not permitted: Immediate processing
When I first published an RFQ, the email notification was sent to vendor and the sent request could be seen in SOST. However, when I changed the RFQ and re-published it, although a new RFQ version is generated, there doesn't seem to be an email notification to the vendor, because there is no SOST entry. Any pointer is appreciated.
I am just following up to see if anybody has similar experience before. We are encountering the same issue in SRM 5.0 (we are at SP15) as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hI JAY
1330173 Changed version not taken in Bid invitation during publish
Is it applicablke for you . now server service.sap is down. kindly check
muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
After checking the code base, I believe this note SHOULD BE applicable to our SP. However, the note itself is having the wrong validity definition (should be > SP05 instead of SP05). So with our current SP level (05), it's not possible to apply the note. I will create an OSS message to SAP for this. Thanks!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.