on 01-25-2010 12:12 PM
When I business complete a PM order 'X', I get following message -
Maintenance Item Y is assigned to X
Maintenence item Z is assigned to X.
The maintenance items Y & Z have order X as settlement receiver in the sttlement rule. These maintenence items are used in a maintenence plan, this plan has only these 2 maintenence items.
What can be done.
Should I set deletion flag to the maintenence plan?
Please advise
Hi,
I think orders from Maintenance item Z and Y are suborders and are assigned to order X . You can first settle Orders from Z and Y maintenance Item and then settle Order X and then do business completion of Order X .
Regards
pushpa