on 01-25-2010 11:48 AM
Hi all,
We have an SRM 7.0 system and EHP 4.0 as our backend system and we wish to enable the service procurement scenario (document exchange between EHP 4.0 & SUS).
I will be using the standard scenario provided by XI/PI to enable this scenario.
But in XI/PI there is a standard scenario provided by SAP by the name "Service Procurement with Supplier Enablement" in which the 2 systems between which document exchange is possible are SRM & SUS instead of EHP 4.0 & SUS(as required by us).
Let me know how to proceed.
Thanks
Nikhil
Hi Nikhil,
For service procurement you can use the following :
SE_Services_Procurement for (MM - SUS)
SE_Sourcing_Enhancements (MM- EBP- MM)
If you use both then the complete business scenario can be completed (MM-EBP-MM-SUS-MM)
Regards
Sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nikhil,
We have a similar requirement as yours.
We are on SRM 7.0 and ECC6 EHP4. The CPPR scenario is active and is working fine for materials and services.
But for MM-SUS we are still using the Idoc method (scenario plan_driven_procurement_SupplierEnablement). So the PO output from SAP is idoc instead of XML.
We want to switch to XML mode to exploit MM SRV-SUS scenario (service procurement classic).
I understand that we now need to configure scenario SE_Services_Procurement in XI instead of plan_driven_procurement_SupplierEnablement. But apart from XI configuration is there any ECC step to be done? We have already activated LOG_MM_P2PSE_1 in ECC. Is there any other change required (over and above existing MM-SUS PDP scenario settings) in ECC?
Regards,
Srivatsan
Pls chek the note 1268336 and 1263876
Regards
Kiran