on 01-25-2010 6:19 AM
Hi
I am through with cost integration for claim and able to generate cost collector (internal order) with order type CL01.
However, the plant value is not updated in the internal order (from WBS or PO, which are referred in claim document).
Due to this i experience the below message when i try to create PO with account assignement to internal order:
"Enter corresponding Internal order for the Plant NB02
Message no. Z1120"
However, by maintaining plant value in internal order (change in KO02), i can use it.
Is there any setting to copy the plant value in the internal order, created automatically through claim?
warm regards
ramSiva
your message number suggests that you are using a custom program
debug that and you should have your answer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.