Hi Experts
The Planning method/Basic and Planning method/forecast field values are grey in my project profile.
What customization would influence for this setting. I wish to change from 2 to 4. Please advise the solution/
warm regards
ramSiva
You can change the above field values only from WBS scheduling profile. If you want to change them, choose 'free scheduling' method.
Regards,
Mahendra