cancel
Showing results for 
Search instead for 
Did you mean: 

Shift dates function to correct start date of PD

Former Member
0 Kudos

Hi Experts

After shifing dates into future, the start date in Project definition (in case of shift back, the finish date in PD) remains same. It is not getting correct according to shift date.

Please suggest possible solution.

warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi Martina

I am using bottom up scenario.

warm regarss

ramSiva

Former Member
0 Kudos

ramSiva,

try deleting the PD end date and extrapolating again...it should work.

Rgds

Martina

Answers (1)

Answers (1)

Former Member
0 Kudos

after Scheduling the project, use function 'extrapolate dates' which will copy in scheduled date in project definitiion.

regards,

Mahendra

Former Member
0 Kudos

Hi

The 'extrapolate dates' function not worked here.

I have schduled project for: 20.01.2010 to 20.02.2010

Then i have shifted the start date from 20.01.2010 to 01.01.2010.

But the finish date in PD remains at 20.02.2010 which should be at 01.02.2010 (proportional shift)

Please suggest the solution for this.

warm regards

ramSiva