Hi Experts
After shifing dates into future, the start date in Project definition (in case of shift back, the finish date in PD) remains same. It is not getting correct according to shift date.
Please suggest possible solution.
warm regards
ramSiva
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
after Scheduling the project, use function 'extrapolate dates' which will copy in scheduled date in project definitiion.
regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The 'extrapolate dates' function not worked here.
I have schduled project for: 20.01.2010 to 20.02.2010
Then i have shifted the start date from 20.01.2010 to 01.01.2010.
But the finish date in PD remains at 20.02.2010 which should be at 01.02.2010 (proportional shift)
Please suggest the solution for this.
warm regards
ramSiva