on 01-22-2010 4:10 PM
Hello experts,
I'm trying to run a GRMG-Lite Szenario using a RFC-Connection to the SLD of a Process Integration System. I created the Scenario on our Solution Manager SP20 (EHP1) in client 000. This solman is our CEN. The RFC-Connection works properly.
When I try to activate the Scenario, it says the scenario was started, but the status is still grey (the deactivated-symbol).
I tried it on another system, there the scenario worked. I also have problems starting any other scenario on this Solman.
I read the prerequisites fpr GRMG monitoring and checked that ICM is active, a sapccmsr-agent is running on the maschine and is registered to the solman.
Has anyone an idea what could be wrong?
Thanks in advance.
Regards,
Maike
Hi,
Can you make sure ICM on ABAP stack works fine.(T-code SMICM).
Below SAP help and OSS notes would help you,
http://help.sap.com/erp2005_ehp_04/helpdata/EN/17/550c404a435509e10000000a1550b0/content.htm
Note 699393 - EP 6.0 SP2: Activating CCMS GRMG heartbeat monitoring fails
615740 - CCMS GRMG Availability Monitoring: FAQ
Regards
Nagaraju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.