PP PI sub operation

thamizhchelvan_gunasekara
Active Participant
0 Kudos

Hi Guys,

Secondary resource assigned in reccipe created as PP-PI sub operation in APO PPM and order scheduled in that operation, though the operation is available in APO order and available in ECC side , and the same is appearing in CCR , is there any way this operation also can be sent to ECC .

Thanks

Thamizh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Thamiz,

The better way would be to create this resource in ECC and CIF to APO. Also, add this to routing and then CIF as PPM/PDS.

Anyway since you are using PPM, you have freedom to make changes in your operations on APO side.

Also, if the resource exist in ECC, please make sure that capacity and scheduling is properly maintained.

Are converting planned orders to production orders?

Regards,

Bipin