Delivery scheduling issue

Former Member
0 Kudos

Hi.

Our users have created a sales order on 20.1.10(wednesday). The required delivery date in sales order is 22.1.10. The system has calculated the material availiblity date as 20.1.10. But this is wrong since i have checked that follwoing is maintained in the configuration of shipping point and route.

In shipping point DE123..........loading time is zero... and Pick/pack time is selected as" route dependent".

In the route DE1234, the transit time is 0.75. there is no transp lead time in route and factory calendar is B10 in route.

so ideally the matrerial avaiable date shud be 22.1.10 less 0.75 days=21.1.10......... but it is 20.1.10 in sales order

my questions are:

1) if pick pack time is route dependent in shipping point. where is pick pack defined in route. i cannot see it in route definition.

2) why system is calculating 20.1.10 ?

3) We have APO too. Is something coming into sales order from APO.

regds

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

"Loading Time" & "Pick/pack time" comes from the Shipping Point.

"Transit Time" & "Transportation Planning Time" come from Route.

In your case, Customer required Delivery date is 22.01.10. Taking this date system starts with backward scheduling first.

Required delivery date - Transit Time = Goods Issue date(21.01.10).

Goods Issue date - Loading Time = Loading date.

Loading date - Pick/Pack Time = Material Availability date(20.01.10).

Therefore, I think system is taking either Pick/Pack time or Loading Time is 1 day for which system is determining 20.01.10 as Material Av date.

Check the lead times in your Shipping point & Route.

Regards

Former Member
0 Kudos

Hi,

"Loading Time" & "Pick/pack time" comes from the Shipping Point.

"Transit Time" & "Transportation Planning Time" come from Route.

In your case, Customer required Delivery date is 22.01.10. Taking this date system starts with backward scheduling first.

Required delivery date - Transit Time = Goods Issue date(21.01.10).

Goods Issue date - Loading Time = Loading date.

Loading date - Pick/Pack Time = Material Availability date(20.01.10).

Therefore, I think system is taking either Pick/Pack time or Loading Time is 1 day for which system is determining 20.01.10 as Material Av date.

Check the lead times in your Shipping point & Route.

Regards