Hi,

I have attached a configurable parent item to Project Activity. It is having Bill of material.

I have put some requirement for this parent item through Project Builder and also i have exploded the Bom for this parent Item.

Now in MRP (MD02/MD04) it is showing requirements only for child items.But requirements for parent item are not visible in Planning.

Can anyone guide as why is this happening ?

Thanks and regards,

Nitin Lavhe

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please sit with your PP Consultant.

Muzamil