Service entry and actvity confirmation

Former Member
0 Kudos

Hi all

My scenerio - we hv activity having work ,duration and servicess. service order is attached to the activity. now i want servicess ( service entry sheet) should be automatically booked when i confirmed activities as same as when i confirm the activities i can also do the goods movement. Is it possible for services ?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In Std SAP,you have to create Service entry sheets against the PO in ML81N.

You cant book the cost directly after confirming the Service Activity.