on 01-21-2010 9:45 AM
Hi Gurus,
I have scheduled my production system to take a daily complete db backup , but when I see the Db12 Database History it shows the last complete backup was happened two days before(ex: 18/01/10 considering today is 21/01/10) and its not showing previous date were the db backup completed. When I checked in OS level the backup is completed for the previous day(eg.20/01/10) which is not showing in DB12. Whether there is any standard jobs that update this log ? My database is DB2.
Please suggest as this is very critical.
Regards,
Rahul
Hi
Check your time zone setting and verify whether all standard jobs are scheduled in 000 client with user ddic
Regards
Yogesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please cross check the following things :
1) Check in SM37 for the DBA* job logs for last 2 days.
2) Whenever backup job is scheduled in DB13, it makes an entry in SAP table "SDBAP". You can also check in this table by the timestamp.
3) Are you able to see backup logs in DB12 before2 days or it is empty ?
Regards,
Ankit