Former Member
0 Kudos

Previously we use IO to capture cost, we have fivty IO already, now we use network activity to capture cost, how to transfer

the IO cost to PS network?

we also have negative amount for some certain network.

how do we settle negative to AUC?

Accepted Solutions (0)

Answers (1)

Answers (1)

shareeq_hussain
Active Participant
0 Kudos

Use the transaction KB11n to transfer cost from I/O to WBS

Regards,

Shareeq

virendra_pal
Active Contributor
0 Kudos

alternatively settle from IO to network activity

Former Member
0 Kudos

thanks. how about settle negative amounts?

virendra_pal
Active Contributor
0 Kudos

that should not be an issue

you should be able to settle negative amounts to AuC

just one thing as you are settling fro IO to NWA

you will need to settle from NWA to WBS

then from WBS to AuC

When you run CJ88 need to tick with order with hierarchy check box

Former Member
0 Kudos

thanks