Alternate delivery type for project delivery

Former Member
0 Kudos

Hi,

I want to know if we can assign multiple delivery types alongwith LP for projpect delivery.

Regards,

Rajesh Mohapatra

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You copy from std and make aternative for LP

But if u want to change immediately at time of delivery creatin you have to option to put PREDEFINED DELIVERY TYPE on initial screen of VL01N

Kapil

Edited by: Kapildev Farakte on Jan 21, 2010 1:02 PM

Former Member
0 Kudos

Hi Kapil,

While creating a delivery from project [CNS0] the option of changing delivery type is not there and no option to change "LP", as it is hard coded. I have found earlier postings wherein I learn that similar request has been refused by SAP.

I have got a typical case wherein we are doing high sea sales from project.

We raise a 3rd party PR, do a statistical GR and then raise a 3rd party delivery thru CNS0.

While doing so a delivery doc is generated without any goods movement and no accounting doc is generated.

The problem is that the customer wants a different number range for such transactions.

Please suggest a solution considering the above scenario.

Regards,

Rajesh Mohapatra