Dear all,
I'm tyring to use easy cost planning for WBS for version 000 and costing variant PS06.
When I tried to call ECP from the projet builder I received this message: "No easy cost planning can be created in version 000"
I've already done these customizing steps:
- assign CO version to ECP
- for costing variant I used PS06 (standard) without any modification
- I have assigned my costing variant to my planning profile
Is someone has already this kind of error ?
Help will be usefull, thanks in advance.
Go to this node Define Alternate CO Version under Easy Cost Planning in SPRO.....there select "PD" Object type and give default CO Version, CO Area and Costing Variant. After that try ECP, It will work.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.