No Easy Cost Planning can be created in version 000

Former Member
0 Kudos

Dear all,

I'm tyring to use easy cost planning for WBS for version 000 and costing variant PS06.

When I tried to call ECP from the projet builder I received this message: "No easy cost planning can be created in version 000"

I've already done these customizing steps:

- assign CO version to ECP

- for costing variant I used PS06 (standard) without any modification

- I have assigned my costing variant to my planning profile

Is someone has already this kind of error ?

Help will be usefull, thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Go to this node Define Alternate CO Version under Easy Cost Planning in SPRO.....there select "PD" Object type and give default CO Version, CO Area and Costing Variant. After that try ECP, It will work.

Former Member
0 Kudos

Thanck you !

Now I'am able to save my entry. But instead of going into ECP screen, I received another message like "Project doesn't contain any/ non calculable plan. elements", my WBS is flagged as a planned element.

Do you have any idea ?

Thanck you so much.

former_member203108
Active Contributor
0 Kudos

No Idea. if you can post the message number or the detail text of the message, it will be helpful.

Answers (0)