cancel
Showing results for 
Search instead for 
Did you mean: 

Scheduler for GRC

Former Member
0 Kudos

Hello,

We have GRC AC 5.3 installed on a Netweaver AS java 7.0 sp20.

Could you tell us if there is a scheduler to manage GRC's jobs, please?

Thank you for your help.

P.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ankur,

I want just have a single interface for all specific jobs for each application GRC.

Especially to monitor and see the jobs who are finished successful.

Is it possible?

former_member366047
Contributor
0 Kudos

You will have to log into each of the specific applications to monitor the jobs in AC5.3.

Thanks!

Ankur

SAP GRC RIG

Answers (2)

Answers (2)

Former Member
0 Kudos

Do you know if CPS (central Process Scheduling) can manage the GRC AC's jobs.

P.

Former Member
0 Kudos

No. GRC AC is an add-on component to NW and is not fully integrated with all the NW featurs.

Alpesh

former_member366047
Contributor
0 Kudos

As Alpesh noted, AC5.3 sits on top of NW and you cannot use CPS to monitor AC5.3 jobs.

Thanks!

Ankur

SAP GRC RIG

former_member366047
Contributor
0 Kudos

As AC5.3 sits on the NW platform, all the application-specific jobs are controlled in each of the applications (CUP, RAR, ERM, SPM).

Are you asking about the application-specific jobs?

Ankur

SAP GRC RIG