Cost relevancy for prelimenary requirement

Former Member
0 Kudos

Hi Experts

Is it possible to set cost relevancy for preliminary requirement item?

warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

for preliminary material planning why do you not use the material planning field

Former Member
0 Kudos

Hi Virendra

I wish to use preliminary planning for specific component (known item) to ensure that material is received intime (not to get effected due to delivery delays). So i wish to generate PR only and no reservation. This will be in stock & as and when required, the goods issue is posted.

Though the material is planned in advance, the cost to be considered in planning. I am not clear why preliminary planning is subject to no cost relevancy.

warm regards

remSiva

virendra_pal
Active Contributor
0 Kudos

basically SAP requires that cost relevany indicator is ticked on

this is done via BOM set up

you will need to create a BOM with the material as part and tick cost relevancy indicator

then when you select preliminary the costing will happen

I will try and simulate

interesting issue !!