Planned POC shows zero

Former Member
0 Kudos

Hi Experts

I have used time proportional method for progress analysis (for activities and WBSs).

The wbs is assigned with network activities.

Before execution, i have run CNE1 and then executed report CNE5.

But i could see the BCWS and not the planned POC. It is shown zero only.

Please correct me if any config missing.

warm regards

ramSiva

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

I have got solution for this. Ref OSS note: 153051.

regards

ramSiva