on 01-18-2010 10:18 AM
Dear All,
I have an issue in proforma invoice, the issue
I need to take proforma based on the schedulines
Suppose for ex: if there is scheduline agreement for x material for 10000 valid from 15.01.2010 to 15.02.2010 and the
schedulines is made for 5000 for two different dates say first 5000 is for 31.01.2010 and another 5000 is for 15.02.2010
when i am doing the proform based on the order i have change in VTFA the billing quanity from "c" to 'D" .
When i am doing profroma based on the order (F5) for the first 5000 i.e (31.01.2010) the billing quantity is coming correct in VF01.
But
When the second proforma for 5000 is done on the scheduline lines i .e for ( 15.02.2010 ) the billing quanity is showing the full qty of 10000 when i wanted to take proforma
The requirement is
the prforma should not show the full quanitty value while taking proforma invoice for the final schedulines
Is this possible , pls guide me on this issue
thanks
Check in sale order what item category is flowing. Then go to VOV7, select your item category and check for the field "Completion Rule" what is maintained. In normal cases, it should have been "B"
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Its not possible to create proforma based on Schedule lines as per standard SAP . It is possible at item level.
REgards,
KRishna O
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.