cancel
Showing results for 
Search instead for 
Did you mean: 

Change order quantity & sales unit in VA02

Former Member
0 Kudos

Hi dear,

Please give me solution for how to change order quantity & sales unit in VA02 for "partially delivered " material.

Thanks & Regards

Amit Karalkar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

1.Sales order you cant change the sales unit for partial deliveries ,

2.You can change only the order quantity which will be above the delivered quantity

my suggestion is to close the Sales Order by putting reason for rejection and create the new sales order with desired quantity

Regards

Damu

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks dear you have solve my issue

Former Member
0 Kudos

Hi,

Once you partial delivered material, then you can not change it's UNIT in sales order,u can only able to change quantity in sales order.

However you can able to change it's unit in delivery note.

but you have to speciefy base & sales unit of measure in material master.

Kapil