Default cost element under external screen tab while creating activity.

Dear all

We had done recently the new patch upload for our system.

Now when we are creating a service activity for project, the system selects by default a cost element no under external tab screen of activity. the no is not maintain in our chart of accounts, neither we had done the default settings.so every time when we creat the activity, we have to remove it manually.

kindly guide me how to remove this cost element so that it should not apppear futher while creating the activity.

Pls let me know the solution as we are facing the problem on PRD server.

Thanks you in advance

regards

parikshit

Former Member
Former Member replied

Hi,

Please refer Notes 1277967 & 1285728.

Regards,

Kabir