delivery date

Former Member
0 Kudos

Dear all

on what bsis delivery date is proposed in sales order

Thanks

jahangir

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Kindly See the below

1.Lead time days maintained in the sales document type --VOV8

2.Calender maintained in the sales org,shipping point & Plant,If any holidays are there system will gives the delivery date on working day.

3.Planned delivery time maintained in the material master

Regards

Damu

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Jahangir,

Different Times involved in delivery scheduling-

 Pick/Pack Time

 Loading Time

 Transportation Lead Time

 Transit Time

Generally system consider the Delivery scheduling on 2 ways i.e. Backward Scheduling and Forward Scheduling

u2022Backward scheduling-The customer request delivery date is used to calculate the material availability date and transportation lead-time. The delivery must be created on the earlier of two dates, if both date are after the order date, the customeru2019s requested delivery date can be confirmed.

u2022Forward scheduling- If both of dates not come after order date, customer request delivery date cannot be confirmed. Now system confirm the quantity on the basis of New Material availability date, the earliest date at which the material is available in the warehouse.

 Two schedule line are generated for the sale line item-

o The date of the first schedule line corresponds to the customeru2019s required delivery date and has no confirmed quantity.

o The date of schedule line shows the confirmed delivery date and the confirmed quantity.

Regards,

Bharat B

Former Member
0 Kudos

Hi

The delivery date is proposed by Transit time, loading time, Pick -Pack time, Transportation planning point...............

cheers

shalsa007..............

Former Member
0 Kudos

Hi,

Delivery dates are poposed by considering Pick,pack,transportation time

Backward scheduling is the calculation of deadline dates: the arrival time at the customer site is calculated as the earliest possible goods receipt time at the customers unloading point on the requested delivery date. All four of the delivery and transportation scheduling lead times are subtracted from the customeru2019s requested delivery date to determine if this date can be met.

The transit time, loading time, and pick/pack time are subtracted from the customeru2019s requested delivery date to calculate the required material availability date.

The system calculates backward scheduling as follows:

Requested delivery date minus transit time = Goods issue date

Goods issue date minus loading time = Loading date

Loading date minus transportation lead time = Transportation scheduling date

Loading date minus pick/pack time = Material availability date

By default, the system will calculate delivery dates the closest day, taking into consideration the working days of the shipping point and a rounding profile. In this case the system assumes a 24 hour work day and lead times can be entered in days up to 2 decimal points. This is referred to as daily scheduling.

Precise scheduling calculated down to the day, hour and minute is supported. This allows the scheduling of a delivery within a single day. It is activated by maintaining the working hours for a particular shipping point.

Backward scheduling is always carried out first. If the material availability date or transportation scheduling date is calculated to be in the past, the system must then use forward scheduling.

Forward scheduling is also done if no product is available on the material availability date calculated by backward scheduling. The system does an availability check to determine the first possible date when product will be available. This new material availability date forms the starting point for scheduling the remaining activities. The loading time, pick/pack time, transit time, and transportation lead time are added to the new material availability date to calculate the confirmed delivery date.

kapil