Hi Gurus,

Pl. corrrect me if iam wrong.. I am assigning a FERT material to one of the nwk. activity under one WBSE. This FERT has a multi level BOM with HALB matl 'x'. I am assigning this HALB material ' x' in another activity Proc. type as Planned indep. reqt. (under the same WBSE) and not chosen Grouping WBS options.

1.My query is that where should I execute the MRP? I understand that I have to execute MRP for FERT. Should I execute for HALB matl. as well because I had assigned it in a separate activity and it consists of its own BOM with another HALB 'y' assigned to it ? or MRP should be executed only for FERT ?

2.When the HALB material is both ( can e produced in-house or procured outside), and I assign Planned indep. reqt. (PIR) as proc. type system generates PR and not PIR. Where i am wrong ?

thanks in advance

Vinodh.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Closed