on 01-11-2010 5:03 PM
Hi Everyone,
We are getting PO's that gett the message "Specify an overall limit" when we do a check on the SC. When I check the limit amountin Item Data they are the same. The PO was create with one value and then changed to increase the value.
Hello,
Check if you have an active implementation of BBP_DOC_CHANGE_BADI. If so, deactivate it temporarily and test the issue.
I've seen cases when trying to change or delete any PO item, this message appeared, but it was due to badi logic.
Kind regards,
Ricardo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have create an OSS note for this issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Umakanth
What we found was that if a Po was in Waiting Approval status and the user tried to change the Po before the approval, that is when we get the error. If the PO is changed while in waiting for approval status and the user uses the "CHECK BUTTON" to validate the changes this is the error that you will get on that PO.
Our Appl Dev group made a modification to the Badi, but felt that this was a SAP issue and we currently have an OSS note. So we have told our users that POs that need approval need to be approved before a change can be made to the PO.
Hope this helps.
Sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.