on 01-11-2010 6:18 AM
Dear Experts
SAP_COLLECTOR_FOR_PERFMONITOR job cancelled continously
can anyone tell me solution
regards
krishna
The job SAP_COLLECTOR_FOR_PERFMONITOR must always be scheduled in client 000 with user DDIC or with a user with the same authorization. (SAP Note 16083)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi krishna,
You may need to provide more information for others to analyze the problem for you.
When did the job start to cancel?
What is the error log for the canceled job?
Did you make any changes during that time?
...
Regards,
Summer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
SAP_COLLECTOR_FOR_PERFMONITOR must run from Client 000 using user - DDIC
Check:
http://help.sap.com/saphelp_45B/helpdata/en/c4/3a7ede505211d189550000e829fbbd/content.htm
Hope that helps.
Hi,
Please paste the Job error log from SM37.
Best Regards
Imran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi imran
see the following error log and give me the solution
Date Time Message text Message class Message no. Message type
08.01.2010 00:30:38 Job started 00 516 S
08.01.2010 00:30:39 Step 001 started (program RSM13002, variant SAP&001, user ID BASISADM) 00 550 S
08.01.2010 00:30:39 Reorganization of Update Data in Batch Not Allowed 15 100 A
08.01.2010 00:30:39 Job cancelled 00 518 A
regards
krishna
Edited by: krishna murthy on Jan 11, 2010 7:46 AM
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |