on 01-10-2010 1:24 PM
I've few mitigating controls in palce with frequency in reports tab as 1. I'm sure that the action given in the reports tab was not executed in the backend system by the monitor but still I do not get alterts for control monitoring in Alert monitor tab. Please advise
Have you scheduled the background jobs for Control Monitoring Alerts generation ?(RAR - configuration tab- background job-alert generation - action monitoring and alert notifications) . If so please check the frequency of the background jobs and their status.
Regards
Swarna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes Frank we followed the note 1088483 - and the monitor has run the transaction once in the backend but still control monitoring alerts do not come in. Unfortunately we have to wait for one complete day to check anything as the frequency is in days. Had the frequency been in hrs. then checking would have been easier.
We made some progress with this. Yesterday I created a new mitigating control this time with riskid as F006*. And today I got the control monitoring alert. I guess the problem was earlier I gave all 9 chanrecters in the risk id field while creating mitigating control. Looks like RAR will not trigger control minitoring alert if you mention 9 character riskid in the mitigating control. If you have other views on this please share.
Plz. note the correction:
It is not 9 character or 5 character risk id that makes the difference. I was not getting control monitoring alert because the 9 character riskid I specified in the mitigating control was a permission level rule id and SAP says that from 5.3 onwards permission rules are not considered for any analysis. So we have to mention the riskid with * or we can specify the action level rule id to receive the control monitoring alerts.