Just have 4 relativley easy questions related to CJCF (Carry Forward Commitment)

1)My project has a PO commitment of 60 USD in year 2009.If I carry forward the commitment using CJCF, will the system just change the delivery date in the PO to the first period of 2010 ?

2)Will the assigned budget value of 60 USD of 2009 move to 2010 with 60USD ?

3)Where can I see the list of carried forward Purchase Orders and its value ?

4) I believe CJCF does not carry forward PR Commitments.Is that a right assumption ?