Just have 4 relativley easy questions related to CJCF (Carry Forward Commitment)
1)My project has a PO commitment of 60 USD in year 2009.If I carry forward the commitment using CJCF, will the system just change the delivery date in the PO to the first period of 2010 ?
2)Will the assigned budget value of 60 USD of 2009 move to 2010 with 60USD ?
3)Where can I see the list of carried forward Purchase Orders and its value ?
4) I believe CJCF does not carry forward PR Commitments.Is that a right assumption ?
Hope to hear from you very soon.Thanks for your help.
Jungleem
Hi,
1)My project has a PO commitment of 60 USD in year 2009.If I carry forward the commitment using CJCF, will the system just change the delivery date in the PO to the first period of 2010 ?
A: No, the delivery dates would remain as it is.
2)Will the assigned budget value of 60 USD of 2009 move to 2010 with 60USD ?
A: That is correct,
3)Where can I see the list of carried forward Purchase Orders and its value ?
A: S_ALR_87013533 transaction
4) I believe CJCF does not carry forward PR Commitments.Is that a right assumption ?
A: That is correct.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Robin for your replies.However, I had some questions :
Does Delivery date not decide the commitment period ? If my commitments get transferred to next year first period, should that not mean that my delivery date has also changed to first period of next year ?
I can see my commitments transferred in S_ALR_87013533 report but CJI5 is still showing the commitments in 2009 report.IS that correct ? I guess, not.
Thirdly, I have observed that CJCF and S_ALR reports both include PR commitments too.
Hope to hear soon.Thanks for your help.
Does Delivery date not decide the commitment period ? If my commitments get transferred to next year first period, should that not mean that my delivery date has also changed to first period of next year ?
A: The delivery date does not get changed but now you cannot post the GR or IR in the old fiscal year.
can see my commitments transferred in S_ALR_87013533 report but CJI5 is still showing the commitments in 2009 report.IS that correct ? I guess, not.
A: This observation is not correct. You should be able to see in both transactions.
Thirdly, I have observed that CJCF and S_ALR reports both include PR commitments too.
A: It includes PR commitments but they are not transferred.
Thanks Robin but I still see commitments in CJI5 for 2009 (is this because CJI5 report is delivery date based, just guessing) and not in 2010.Where as I see commitments in 2010 in S_ALR report.I ran some correction programs too but that did not change the CJI5 reporting.
I also see PR commitments too transferred to 2010.I also see no logic as to why they should not be.
I welcome any response.Thanks.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.