sceduling -problem

Former Member
0 Kudos

Dear all

Scheduling does not happening in master recipe

i have checked following point

Resource -formula

planned scheduling parameter

process order scheduling paramete

I have used same resource and material in routing there scheduling working fine.

Kindly help

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

thx

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check the scheduling type in OPUZ and OPU5 it should be Backward scheduling with automatic scheduling

In resource in capacity tap check the have you define the,

Factory calendar ID 01

Active version 1

Base unit of meas. H

Start 00:00:00

Finish 24:00:00

Length of breaks 00:00:00

Relevant to finite scheduling Tick mark.

Control key should mark for scheduling and check formula also.

In master reciepe you have option for scheduling. go to transaction C202, and from menu you would find the option to schedule the recipe.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear all/R Brahmankar

I am using std sap scheduling formula ( SAP002 for processing ,SAP003 for tear down) in resource

i checked i got following below message "Scheduling without component quantities

Message no. C5641

dhaval_choksi3
Active Contributor
0 Kudos

Dear Harish,

This formulas are not suitable for PI(Master Recipe).

In both of this Formula (SAP002, SAP003) parameter SAP_11 - Operation Splits is used.And Its value will be fatch from Routing - Rate Routing during scheduling calculation.But up to my knowledge in Master Recipe there is no such field (Field name is SPLIM)

So it might possible that in Routing/ production order it works fine but when it comes to master recipe/process order it doesn't work.

You need to work around some other formula.

Regards,

Dhaval

Edited by: Dhaval on Jan 8, 2010 8:14 PM -

Field name is added

Former Member
0 Kudos

Hi,

where have you entered the formula for scheduling in resource scheduling tab ?

Try "Other formula" field

Former Member
0 Kudos

Hi,

Check the factory calender settings of the factory calender is active.

former_member207022
Active Contributor
0 Kudos

Check your control key whether scheduling indicator is enabled.

Former Member
0 Kudos

scheduling is already activated in control key