on 01-07-2010 3:14 PM
We would like to do confirmation with old date.
Is it possible in EBP.
For example: todays date is 07.01.2010 . I wants to be affected in my Financial postings with date 01.01.2010.
I have used the date field in the Confirmation screen but still it is showing that this has been done today.
erpman
the mentioned behavior is standard in SRM .
however lokk into this below note
Note 486124 - Entering posting date
When a goods receipt or a service is confirmed, the posting date is to be entered (different from the document date).