Impact of Movement type 231 after PGI of delivery

former_member227232
Active Contributor
0 Kudos

Hi,

We have a requirement to issue some components to Sales Order for which we have already done Delivery.

We don't want to reverse PGI & add the components.

It is to backflush these components.

Will there be any subsequent impact if manually issue in MB1A using Movement Type 231?

Regards,

Vengat

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Why not you create an another delivery in place of doing through MB1A with move type 231.

If you do the goods issue with MB1A, it will not refect in sales order document flow and you will not be able to bill to customer, because for billing you need delivery docuement (with PGI complete Status) if billing is delivery relevant.

regards

Vivek.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

If you Issue components after delivery, it will not reflect in sales dcoument flow, becauze data gets already compiled in sales order as well as in delivery,also you comleted PGI too.

Kapil