on 01-07-2010 10:37 AM
Dear All
Is it possible to close the project without making revenue settlement. If it is possible how to do Please explain in detail.
I get the below error msg while trying to close the project.
Balance of WBS xxxxxxxxxxxx- is not zero
Message no. KO505
rgds,
senthilkumar N.K
95908 37102
Are you running RA? If you are running RA, then you must have to settle it.
Otherwise, as suggested by Virendra, you can change your settlement profile & close the project.
--Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amaresh
Even if you are running RA you can have settlement rule "can be"
The settlement incase of RA would then only do the financial posting and not anything to PSG
As the error is balance of WBS is not zero - it means that settlement has been set mandatory, this needs to be removed
Regards
Virendra
change your settlement profile to Can be settled from must be settled
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.