How to transfer budget from one WBS to WBS

Former Member
0 Kudos

Dear All,

Please guide me how to transfer budget from one wbs to second wbs.

Also tell me how can i see used budget against any project

Regards,

Mahesh Wagh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

The standard method is to use T Code CJ34 to transfer the budget from one WBS element to the other.

Regards,

Vinodh.

virendra_pal
Active Contributor
0 Kudos

Vinodh is correct

use CJ34 not CJ30, also check out CJ36 and/or CJ37

Regards

Virendra

Former Member
0 Kudos

I am sorry, I missed it completely ! Thanks Vinodh and Virendra for correcting me.

Regards,

Mahendra

Answers (1)

Answers (1)

Former Member
0 Kudos

You can transfer budget in transaction CJ30. Just remove amount from the WBS to the WBS where you want to allocate.

In the report S_ALR_87013558, you can see the available figure as figure available still from budget.

Regards,

Mahendra