impact on schedule lines

Former Member
0 Kudos

hi,

i have created a sales order.

and then i changed the GI date to next day.

what is the direct impact on scheduling the sap system.

will there be a positive impact or negative impact or no impact, particularly on the scheduling.

regards,

balajit

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Requested Delivery Date: Requested delivery date is the date on which the material should be delivered to the customer at his location.

Date for Availability Check: Availability is checked on the material availability date.

Material Availability Date: Material Availability date is the date on which the material should be available in order to confirm the customeru2019s requested delivery date. On this date, you must begin picking, packing, labeling, and loading the goods.

It is determined by carrying out backward scheduling from the customers requested delivery date.

To match the request delivery date system first do the backward scheduling and if it is not matching system will do the forward scheduling.

Backwards Scheduling: Backward Scheduling is the scheduling of delivery related activities in the backward direction from the requested delivery date to determine Material Availability date.

Forward Scheduling: Forward Scheduling is the scheduling of delivery related activities in the forward direction from Material Availability Date to the requested delivery date.

regards

Vivek.

Answers (1)

Answers (1)

Former Member
0 Kudos

HI