Hi Experts,
In Source Inspection Scenario there is a requirement, before GR quality wants to accept partial qty.
Ex: I st case: As per PO qty 10 PCs after inspection 6 accepted and 4 rejected during GR system should allow accepted qty only.
IInd case: As per PO qty 10pcs he will inspect and accept 2 qty and system should allow only for 2 qty not for all 10 qty.
How it is possible kindly explain me
Inadvance Thanx
Shiva Patil
Hi
Its not possible to have partial Qty GR for the source inspection as there is no stock posting screen in the souce inspection.
Either you have to accpet all or reject all
Regards
Sujit