on 01-05-2010 1:13 PM
hi,
my basic unit of measure is EA, and while creating condition record my frieght condition type kf00 is taking per tonne only.
all the prequisities are given like:
i uploaded my materials in EA.
& by default in MMR i have kept conversion factor as 20 EA = 1Tonne.
when i raise sales order it is not calculating my frieght amount in to EA but it is taking in tonnes.
regards,
balajit
The standard KF00 is defined as a calculation type of "Gross Weight" Try changing that to "Quantity"