Hi Experts

The crtitical activities in a project can be visualized in PPB/Gantt chart.

Is there any specific program or report to evaluate critical activities apart from this graphic?

warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Kudos

Hello,

Check if the transation CN24N is available in your system. This transaction has a monitor functionality, and you can implement the Badi to show the critical activity, e.g. using a speicial color or icon.

Kind regards,

Zhenbo

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

none that I know

you can use activity overview where float = 0 means critical