1. I have an interview question

Is it posible to do credit check at base value say pr00 value, generally credit check is done at netvalue, all open items or total value but at base value is is possible

2. Tcode for list of customers

3. Can we delete CMR if yes how can we delete, if not why we can delete

4. What is the system landscape of your latest client

5. How shipment calculation can be done and what r the necessary configuration settings to carry out shipping calculation

6. Is solution manager is implemented in ur company, how and why a SD functional consultant can use

your immediate response is highly appreciated

thanks

sateesh

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member266852
Active Contributor
0 Kudos

Hi

Here is more details in your question.

1. Is it posible to do credit check at base value say pr00 value, generally credit check is done at netvalue, all open items or total value but at base value is is possible

Ans : Basically in your pricing procedure there is a coloum Subtotal with option A "Carry over price to KOMP-CMPRE (credit price)" it means whichever condition type you will maintain this option system will carry the credit check against the value of that condition type.

2. . Tcode for list of customers

Ans. For standard SAP t-Code is VCUST, for table level go to SE11 and use table KNA1(for General) KNVV (for sales)

3. Can we delete CMR if yes how can we delete, if not why we can delete

Ans. Generally master data which is created in SAP you can not delete. You can only block the customer master for overall or some specific sales area level

4. What is the system landscape of your latest client

Ans. This is totally depands on customer. Some customer keep system landscape like DEVELOPMENT - QUALITY - PRODUCTION

Whereas some client keep DEVELOPMENT - QUALITY - PRODUCTION - SENDBOX (REPLICA OF PRODUCTION SERVER for R&D or for support teams research purpose)

5. How shipment calculation can be done and what r the necessary configuration settings to carry out shipping calculation?

Ans. This question is not cleared that what u required whether shipment cost calculation or transportation time calculation

For Shipment cost you have to make setting in SPRO -- LOGISTIC EXECUTION -- TRANSPORTATION ---SHIPMENT COST (here you maintain the config of shipment cost)

6. . Is solution manager is implemented in ur company, how and why a SD functional consultant can use

Ans. Solution manager is very important implemantation tool. It is kind of document repository where u maintain all information of variouse implemantation steps. It is one place where you maintain the all information of project (whether project related issue with their processing status or other imformation)

Regards

Shambhu Sarkar

jignesh_mehta3
Active Contributor
0 Kudos

1. Credit Check at Base Value - Maintain Subtotal - "A" against condition Type PR00 in Pricing Procedure.

2. T-Code: VCUST

3. CMIR is master Record. WE cannot delete any Master Record, we can only flag it ffor Deletion...

4. System Landscape: Development - Quality - Production or Development - Production, or as t he actual case may be...

6. Can be used by SD Consultant or Tracking & Updating End-Users Tickets.

Former Member
0 Kudos

Sorry, you all failed someone else's interview, by answering.

Thread locked.

Former Member
0 Kudos

Hi

Please find the answers below

1.Kindly maintain the subtotal 'A' against the condition type PR00 in the pricing procedure then system check the credit value against the PR00 value

2.There is no standard T code for list of customers you can try XD03 ,OV50 & OV51

3. we cant delete the CMr we can only ut the deletion flag for CMR in the T code XD06 or VD06

4 Basic land scape Development----Quality -


Production

Regards