Hi Gurus,

I have noticede that whever we transfer PPM to SCM system, activity time in PPM is defined in Hrs only.

Eventhouh we specify timiings in R/3 routing in min or sec, still PPm displays in Hrs only with apprppriate conversion.

Our requirement is to display time in PPM in min & not is Hrs

Is there any way to fix this issue?

with regards

Mangesh A. Kulkarni

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Mangesh,

In R/3 change the Base Unit of measure in the affected Workcenter to MIN

CR02>Capacity tab>Capacity Header Look in the Available capacity block, change Base U/M to MIN or whatever you want to appear in your PPM..

You will have to re-create and re-cif the PPM across. Existing orders using the 'old' version of the PPM may have to be managed.

Rgds,