on 01-05-2010 4:58 AM
Hi Gurus,
I have noticede that whever we transfer PPM to SCM system, activity time in PPM is defined in Hrs only.
Eventhouh we specify timiings in R/3 routing in min or sec, still PPm displays in Hrs only with apprppriate conversion.
Our requirement is to display time in PPM in min & not is Hrs
Is there any way to fix this issue?
with regards
Mangesh A. Kulkarni
Mangesh,
In R/3 change the Base Unit of measure in the affected Workcenter to MIN
CR02>Capacity tab>Capacity Header Look in the Available capacity block, change Base U/M to MIN or whatever you want to appear in your PPM..
You will have to re-create and re-cif the PPM across. Existing orders using the 'old' version of the PPM may have to be managed.
Rgds,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.