on 01-04-2010 6:11 PM
Hi ,
i have problem creating PO confirmations in SUS to SRM (6.0).
i have a PO with 2 items (SUS and SRM)
PO
->item1
->item2
when i confirm a PO in SUS, a confirmation is sent via XI to SRM .
but the confirmation is created with hierarchy in SRM and in SUS is ok.
Conf BUS2233 SUS
->item1
->item2
fo
Conf BUS2203 SRM
-HIER1
->item1
-HIER2
->item2
If the PO does not have hierarchy, then the confirmations
also will not have any hierarchy item. true??
is this a configuration problem in SPRO problem ? any sugestions ?
Thanks and Regards
Luis
I´ve solve the question with SAP OSS note 1070555 .
Regards